    CAG Report Flags Deep Governance Failures in J&K: 231 NABARD Projects Incomplete, IFMS Delayed by Over a Decade
    September 30, 2026
    J&K Assembly Passes Statehood Resolution Amid BJP Protests; Omar Abdullah Says Delay Would Leave Decision to Pakistan
    September 28, 2026
    When 8 BJP MLAs Backed NC’s Autonomy Resolution in J&K Assembly: The 2000 Chapter Resurfaces
    September 26, 2026
    ASSEMBLY STORM: J&K Govt Caught Dodging ‘One Vehicle–One Officer’ Rules as Speaker Demands Fresh Reply
    September 24, 2026
    “A Matter of Dignity”: J&K Assembly Passes Landmark Resolution Seeking TET Exemption for In-Service Teachers
    September 24, 2026
  • Latest
    LatestShow More
    J&K Bureaucrats vs. Ballots: CS, LS Face Breach of Privilege for Directing Speaker on Statehood Resolution
    September 30, 2026
    Salary Bills stalled: CM says “won’t pass without unanimity” as BJP cites job crisis
    September 29, 2026
    ‘Hysteria Patients’: Congress MLA Bhat Takes on BJP During J&K Statehood Debate
    September 28, 2026
    Omar challenges BJP on statehood in Assembly: “If you support it, vote for it”
    September 25, 2026
    Slogan War in J&K Assembly: BJP and NC Clash Over “Cylinder Chor” and “Chanda Chor” Taunts
    September 24, 2026
  • Editor
    EditorShow More
    ‘Duty Confines Us to Few Hours, Seva Encourages 24X7 Commitment to Nation’: Prof B S Sahay
    August 20, 2026
    Between Slogans and Reality: The Political Arithmetic of Women’s Empowerment
    April 18, 2026
    Explosions, Dead Associates, and a Life Sentence Threat—The Bizarre Conspiracy Surrounding Ankit Love
    March 13, 2026
    Surankote MLA Seeks Update on Bufliaz–Surankote Road; Govt Sets New Completion Date for July 2026
    October 28, 2025
    500 Errors Detected and Rectified in Digitized Land Records of Qaimoh Tehsil, Says Government
    October 28, 2025
  • Opinion
    OpinionShow More
    Alarming Rise of Drug Addiction and Risky Behavior Among J&K’s Youth
    June 30, 2025
    Administrative Leadership Challenges in Health Department of J&K
    June 22, 2025
    Strengthening Patient Care and Trust: “A Strategic Framework for Healthcare Reform in Jammu and Kashmir”
    June 2, 2025
    Analysis: Operation Sindoor, India’s Silent Battle Against the Fog of Fake News
    June 2, 2025
    The Rising Price of Flour: A Burden on the Common Citizen
    January 21, 2025
Reading: CAG Report Flags Deep Governance Failures in J&K: 231 NABARD Projects Incomplete, IFMS Delayed by Over a Decade
Share
The Hidden NewsThe Hidden News
Search
  • Home
  • Exclusive
  • Latest
  • Editor
  • Opinion
Follow US
The Hidden News > Blog > Exclusive > CAG Report Flags Deep Governance Failures in J&K: 231 NABARD Projects Incomplete, IFMS Delayed by Over a Decade
Exclusive

CAG Report Flags Deep Governance Failures in J&K: 231 NABARD Projects Incomplete, IFMS Delayed by Over a Decade

Editor
Last updated: September 30, 2026 7:48 pm
Editor Published September 30, 2026
Share
SHARE

42 UT Public Sector Enterprises Under Scanner; Rs 461.67 Crore NABARD Funds Remain Unutilised

Avinash Azad

The Comptroller and Auditor General (CAG) of India has flagged widespread financial and administrative deficiencies in Jammu and Kashmir, with only 32 of 263 NABARD-funded projects due for completion having been finished by March 2023.

The findings are part of CAG’s, Report No. 3 of 2026, Composite Audit Report (CAR) on Civil and Public Sector Enterprises, tabled in the Jammu and Kashmir Legislative Assembly on Wednesday, the last day of the autumn session.

According to the report, 231 of the 263 projects were either incomplete or had not started as of March 2023. Against Rs 844.17 crore released between 2018 and 2023, only Rs 382.50 crore, around 45 per cent, was spent, leaving Rs 461.67 crore unutilised.

The CAG said delays undermined the intended objectives of improving irrigation, flood management, drinking-water supply and rural road connectivity.

The Union government had consented to loans of Rs 3,900 crore from NABARD during 2018-19 to 2022-23. However, the Jammu and Kashmir administration availed only Rs 2,316.37 crore, or 59 per cent, of the approved amount.

The report noted that NABARD’s disbursement ranged between 28 per cent and 84 per cent of the sanctioned loans across different tranches, primarily because of the slow progress of works. In several cases, loans lapsed because prescribed timelines were not followed.

The CAG observed that project planning and prioritisation by the executing departments were weak. Baseline data and planning frameworks required under NABARD guidelines were either unavailable or not effectively used while selecting projects.

Several projects were sanctioned or executed without ensuring basic prerequisites, including availability of encumbrance-free land, forest and other statutory clearances, identification of viable water sources and approval of technically sound detailed project reports.

The audit also pointed to diversion and misutilisation of funds, defective DPRs, improper site selection, inadequate contract management and delays in releasing funds.

As of March 31, 2023, Jammu and Kashmir had 42 public sector enterprises under the CAG’s audit jurisdiction. Of these, six were inactive and 36 were active. While 11 enterprises were profit-making, 20 reported losses amounting to Rs 252.53 crore in 2022-23. The net worth of 14 enterprises had been completely eroded by accumulated losses. The combined reported profit of the enterprises increased to Rs 1,286.79 crore in 2022-23 from Rs 566.10 crore in 2021-22. However, only Jammu and Kashmir Bank Limited had declared or paid a dividend.

The CAG recommended that the administration take an early decision on liquidation of inactive enterprises and initiate corrective measures to improve the performance of loss-making public sector companies.

The audit raised serious concerns over delays in presenting financial statements for audit. Of the 34 enterprises whose accounts for 2022-23 were due, only four had submitted their financial statements for CAG audit by September 30, 2023.

The accounts of 19 enterprises had been in arrears for three years or more. The accounts of the Jammu and Kashmir Road Transport Corporation and the Jammu and Kashmir and Ladakh Financial Corporation were also pending for two years or more. The audit of Jammu and Kashmir’s Integrated Financial Management System (JKIMFS) found major technical, administrative and security deficiencies.

The system, initiated in March 2010, was intended to provide comprehensive financial management and real-time monitoring of the government’s fiscal position. However, as of March 2023, only four of the 12 proposed modules were fully operational, resulting in a delay of more than a decade in implementing the complete system. The CAG said Jammu and Kashmir lost central assistance of Rs 11.88 crore because the Detailed Project Report was not revised as required and prescribed milestones for treasury computerisation were not achieved. The report further highlighted weak logical access controls, inadequate password recovery mechanisms, absence of complete transaction logs and lack of a comprehensive disaster recovery and business continuity plan.

You Might Also Like

J&K Assembly Passes Statehood Resolution Amid BJP Protests; Omar Abdullah Says Delay Would Leave Decision to Pakistan

When 8 BJP MLAs Backed NC’s Autonomy Resolution in J&K Assembly: The 2000 Chapter Resurfaces

Omar challenges BJP on statehood in Assembly: “If you support it, vote for it”

Slogan War in J&K Assembly: BJP and NC Clash Over “Cylinder Chor” and “Chanda Chor” Taunts

ASSEMBLY STORM: J&K Govt Caught Dodging ‘One Vehicle–One Officer’ Rules as Speaker Demands Fresh Reply

TAGGED:CAG Report 2026Comptroller and Auditor GeneralFinancial Irregularitiesgovernment auditIFMSinfrastructure projectsJ&K AssemblyJammu Kashmir NewsNABARD projectsNABARD-RIDFpublic financepublic sector enterprisesrural infrastructure
Share This Article
Facebook Twitter Email Print
Leave a comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Follow US

Find US on Social Medias
FacebookLike
TwitterFollow

Weekly Newsletter

Subscribe to our newsletter to get our newest articles instantly!

[mc4wp_form]
Popular News
Exclusive

CAG Report Flags Deep Governance Failures in J&K: 231 NABARD Projects Incomplete, IFMS Delayed by Over a Decade

Editor Editor September 30, 2026
J&K Bureaucrats vs. Ballots: CS, LS Face Breach of Privilege for Directing Speaker on Statehood Resolution
Salary Bills stalled: CM says “won’t pass without unanimity” as BJP cites job crisis
‘Hysteria Patients’: Congress MLA Bhat Takes on BJP During J&K Statehood Debate
J&K Assembly Passes Statehood Resolution Amid BJP Protests; Omar Abdullah Says Delay Would Leave Decision to Pakistan
- Advertisement -
Ad imageAd image
Global Coronavirus Cases

Confirmed

0

Death

0

More Information:Covid-19 Statistics

Categories

  • Exclusive
  • Latest
  • Editor
  • Opinion
  • About us
  • Contact
  • Advertise With Us

About US

We influence 20 million users and is the number one business and technology news network on the planet.
Quick Link
  • My Bookmark
  • InterestsNew
  • Contact Us
  • Blog Index
Top Categories
  • My Bookmark
  • InterestsNew
  • Contact Us
  • Blog Index

Subscribe US

Subscribe to our newsletter to get our newest articles instantly!

[mc4wp_form]
©2024 The Hidden News. All Rights Reserved.
WhatsApp
Hello 👋
Can we help you?
Open chat
Powered by Joinchat
Welcome Back!

Sign in to your account

Register Lost your password?